Types of Roofs

Shingle Roof

PROCESS:

-Tear-off the existing roof

 

-Replace rotten plywood (if necessary)

 

-Re-nail plywood with 2 1/2 inch nails

 

 -Install 30 pound asphaltic paper with asphalt roofing roll with tin tag and nails 1 ¼

 

-Install Timberline GAF Shingles

 

-Install all LED pipe, drip edge 3/3 and valley metal

 

-Sweep entire yard, including shrubs, with magnet to find and remove all old nails and new screws

 

-Remove all debris from premises

Tile Roof

PROCESS:

-Tear-off the existing roof (including all materials; 30LB roll, 90LB, tiles, lead pipe boots, galvanized metal vent stacks, and valley metal)

 

-Replace rotten plywood (if necessary)

 

-Re-nail plywood with 2 1/2 inch nails

 

 -Install 30 pound asphaltic paper with asphalt roofing roll with tin tag and nails 1 ¼

 

-Hot mop 90LB or polystick

-Install tiles with foam A and foam B

 

-Install all LED pipe, drip edge 3/3 and valley metal

-Install galvanized metal 26 gauge flashing

-Flashing white Epoxy Paint

 

-Sweep entire yard, including shrubs, with magnet to find and remove all old nails and new screws

 

-Remove all debris from premises

Metal Roof

PROCESS:

-Tear-off the entire existing roof (including all materials; 30LB roll, 90LB roofing tiles, lead pipe boots, galvanized metal vent stacks, and valley metal) down to the wood roof deck

- Replace rotten plywood (if necessary)

- Re Nail plywood with 2 ½ inch nails

- Install 30LB roofing roll with tin tag and nails 1 ¼

- Install GAF versa shield fire barrier 

- Install Standing Seam metal panel

- Sweep entire yard, including shrubs, with magnet to find and remove all old nails and

new screws

- Remove all debris from premises

Flat Roof

PROCESS:

 

-Tear-off the entire existing roof (including all materials, Base Sheet 75LB roll roofing, R-20 roofing roll, Cap sheet, lead pipe boots, galvanized metal vent stacks, and valley metal)

-Replace all the rotten plywood

-Re nail plywood with 2 ½ inch nails

-Install newly-felted roof deck 75 pound with nails 1 1/4 inch and tin tag

-Install R-20

-Solidly hot-mop newly-felted roof deck with premium single-ply cap sheet roll roofing

-Install drip edge 3/3” gooseneck and all flashing.

-Sweep entire yard, including shrubs, with magnet to find and remove all old nails and new screws, Remove all debris from premises